For logistics and installation teams

Plan Packing, Transport, Lifting and Site Interfaces Before Production

Answer first

Package geometry, route limits, foundations, cranes, storage and installation responsibilities must be reviewed before the manufacturing release.

Cargo and packing inputs

  • Component or module dimensions, weights and lifting points
  • Protection, identification, sequence and container strategy
  • Customs, quarantine and dangerous-goods checks where applicable
  • Shortage, damage and replacement-record process

Port and inland route review

  • Origin and destination ports
  • Transshipment, island or oversize transport
  • Road, bridge, height, width, turning and access constraints
  • Delivery windows, permits and staging areas

Site receipt and storage

  • Unloading area, crane setup and exclusion zones
  • Wet-weather and long-duration storage protection
  • Arrival inspection and traceable package reconciliation
  • Sequence aligned with foundations and work fronts

Foundation and installation interfaces

  • Survey control, tolerances, levels and hold-downs
  • Temporary works, bracing and installation sequence
  • Local licensed trades and MEP connections
  • Inspection, concealment, testing and handover gates

Responsibility boundaries

  • The owner appoints local delivery and construction parties
  • ExportPrefab coordinates agreed China-side cargo and installation information
  • Local contractors control site safety and execution
  • Final responsibilities are confirmed in the project scope and contract

Start with the available project facts

Unknown early-stage information can be marked as not known. The review will identify the next useful inputs.